Broadband update — May 2023

By
Posted on May 08 2023 in Steuben County REMC

Phase 1 (5 zones, all open) | Orland/West Otter/Salem/Helmer

At-home installation (all zones open)

Phase 2 (Zones 1 of 4 open) | Nevada Mills/Lake James/Crooked Lake

  • Registration open
  • Make ready construction (complete)
  • Mainline construction (complete)
  • Mainline splicing (Zone 7 Nevada NE)
  • Service wire construction
  • At-home installation (Zone 6 Nevada North)

Phase 3 (6 Zones) | North-Central-East Angola/Fremont
Construction starting after Phase 2

  • Registration open
  • Make ready construction

Phase 4 (4 Zones) | South-East Angola/Ashley/Hudson

Construction starting after Phase 3

  • Registration open
  • Make ready engineering