Broadband update: June 2023

By
Posted on May 31 2023 in Steuben County REMC

Phase 1 (5 zones, all open) | Orland/West Otter/Salem/Helmer

At-home installation (all zones open)

Phase 2 (zones 1 of 4 open) | Nevada Mills/Lake James/Crooked Lake

Registration open

Make ready construction (complete)

Mainline construction (complete)

Mainline splicing (Zone 7 nevada ne)

Service wire construction

At-home installation (zone 6 nevada north, Zone 7 nevada ne)

Phase 3 (6 zones) | North-Central-East Angola/Fremont. Construction starting after Phase 2

Registration open

Make ready Construction (complete)

Mainline construction

Phase 4 (4 zones) | South-East Angola/Ashley/Hudson. Construction starting after Phase 3

Registration open

Make ready Engineering (complete)