The map above is color-coded to represent the different phases of the Orange County Fiber high-speed internet project. Listed below are more detailed statistics on the construction progress as of March 12:
- Crews are currently working in the areas near Hardinsburg and Campbellsburg.
- Approximately 900 miles of fiber is now up.
- Approximately 3,600 drops have been installed to homes.
- Over 3,000 members are connected and using the new high-speed internet service.
Phase I – COMPLETE (noted by the light blue in the map below)
Phase II – COMPLETE (noted by the medium blue in the map below)
Phase III – Current Construction (noted by the dart blue in the map below):
- Make Ready Complete. Mainline construction began in March. Estimated completion in May. Splicing and testing to follow. Service installs to begin in June.
- Mainline construction complete. Currently constructing drops. Service installs to begin in April.
- Ready for service installs/currently installing.
- Ready for service installs/currently installing.